  • 35kV cable handover test plan, on-site operation record of relay protection tester

    With the increase of distribution network transformation and new energy grid connection projects, the use of relay protection testers is also expanding. Recently, there have been multiple technological renovation projects involving the selection, configuration, and use of relay protection testing equipment. The following is a summary of some experience gained during the project implementation process.

    6 Phase Relay Tester

    1、 Equipment configuration in distribution network renovation project

    The 2025 distribution network renovation project in a certain region involves equipment updates for 12 35kV substations, among which the relay protection testeris the main item in the procurement list of testing equipment.

    1. Configuration plan: Based on the equipment types and voltage levels covered by the project, three different specifications of relay protection testers have been selected to meet all testing requirements.

    2. Procurement cycle: The entire procurement process, from the preparation of technical specifications to the acceptance of equipment upon arrival, takes about 45 days.


    2、 Testing requirements for new energy power plants

    The grid connection testing of photovoltaic power plants and wind farms has different requirements for relay protection testers, and the equipment configuration scheme of traditional power testing needs to be adjusted accordingly.

    1. Photovoltaic power station: Insulation testing of inverters, box transformers, and combiner boxes is a necessary project before grid connection, requiring relay protection testers to have measurement capabilities suitable for DC systems.

    2. Wind farm: The detection environment conditions for wind turbine tower foundations and box transformers are poor, and it is recommended to choose relay protection tester models with higher protection levels.


    3、 Feedback on the use of relay protection tester in different projects

    We have collected actual usage feedback from several units, and the following issues have repeatedly occurred in multiple projects, which are worth paying attention to in subsequent procurement and usage.

    1. Low temperature start-up issue: When the winter temperature in northern regions drops to minus 15 ℃, the LCD screen response of some relay protection testers slows down. It is recommended to choose a wide temperature screen model.

    2. Outdoor power supply: Some outdoor construction sites do not have mains power, and the battery life of relay protection testers becomes a limiting factor, requiring backup generators or high-capacity mobile power sources.


    4、 Collaborative use scheme with zinc oxide lightning arrester comprehensive tester

    In the comprehensive maintenance project, the relay protection tester needs to work in conjunction with the zinc oxide lightning arrester comprehensive tester. Reasonable equipment scheduling and personnel arrangement can effectively shorten the maintenance period.

    1. Equipment scheduling: When multiple detection tasks are parallel, it is recommended to group them according to voltage level and equipment type, and each group should be equipped with one relay protection tester and one zinc oxide lightning arrester comprehensive tester.

    2. Data integration: The testing data of each group should be summarized on the same day on a unified platform for the project technical leader to evaluate the overall progress and quality.


    5、 Subsequent maintenance and training arrangements

    After the new equipment is in place, training and daily maintenance are equally important. A sound training system can reduce the risk of human error and extend the service life of equipment.

    1. Operation training: The manufacturer's technical personnel should attend the training for 1 to 2 days, covering the basic operation, safety precautions, and simple troubleshooting of the relay protection tester.

    2. Ledger management: Establish an equipment ledger for relay protection testers, recording equipment numbers, purchase dates, calibration records, and maintenance history.


    FAQ

    Q1: Can the same relay protection tester be used for new energy grid connection testing and traditional power testing?

    A1: It is necessary to confirm whether the AC/DC measurement range of the equipment covers the parameter requirements of the new energy system, and some scenarios may require additional configuration of adapters.

    Q2: What approval procedures are required for the procurement of relay protection testers in technical renovation projects?

    A2: Generally, the technical department needs to propose requirements, the biotechnology department reviews technical parameters, the material department organizes procurement, and major projects also require approval from company leaders.

    Q3: Who should I contact if there are still any issues after the equipment training?

    A3: First, consult the operation manual and common problem document. If you cannot solve the problem, you can contact the manufacturer's technical support hotline. Wuhan UHV provides lifelong technical services.

    Bạn cũng có thể thích

    • Có bất kỳ câu hỏi nào!

      ĐỪNG ngần ngại LIÊN HỆ VỚI CHÚNG TÔI BẤT CỨ LÚC NÀO
      Liên hệ chúng tôi
    • Ghé thăm chúng tôi

      Tòa nhà 6, Khu công nghiệp Cơ khí Quang học Thung lũng Quang học, 84 Đường Gaoxin 5,
      Khu phát triển công nghệ mới Hồ Đông, thành phố Vũ Hán, tỉnh Hồ Bắc, Trung Quốc

    • Gửi email cho chúng tôi

      qiao@hvtest.cc

    • Gọi cho chúng tôi

      +86-15871365102